杭州湾跨海大桥南岸接线高速公路深厚软基处理

Treatment technology for deep and thick soft foundation of south linkage expressway of Hangzhou Bay Cross-sea Bridge

  • 摘要: 介绍了杭州湾跨海大桥南岸接线高速公路工程及区内深厚软基基本情况, 通过前期先导试验段研究提出了深厚软土地基处理的原则性设计方案及其精细化设计计算方法、施工工艺和施工管理及质量控制措施, 并形成高速公路深厚软土地基处理成套技术。采用该技术指导完成了杭州湾跨海大桥南岸接线高速公路工程和宁波地区其他高速公路软土地基的加固处理, 分析加固处理效果, 结果表明深厚软土地基处理成套技术应用效果较为理想。

     

    Abstract: This paper introduces the basic situation of a deep soft soil foundation in the south linkage expressway engineering of the Hangzhou Bay Cross-sea Bridge. Through the preliminary studies of the pilot experimental sections, a principle design scheme and the fine design and calculation methods, construction technology, construction management as well as the quality control measures for the deep and thick soft soil foundation treatment were proposed and discussed, which forms a complete technology for the deep and thick soft soil foundation treatment of the expressway. And the soft soil foundation treatment of the south linkage expressway of the Hangzhou Bay Cross-sea Bridge and other expressways in the Ningbo region was finished by the use of the complete technology. The analysis of the foundation treatment effects is carried out in this study, and from the construction practices it is found that this complete technology for the deep and thick soft foundation treatment has been successfully applied to the similar works, which shows that the application effect of the deep and thick soft soil foundation treatment technology is relatively ideal.

     

/

返回文章
返回